Imagine a situation: in the spring, a farmer is planning to plant corn and expects to sell the harvest in the fall at approximately 10,000 UAH per ton. It is precisely taking this price into account that he purchases seeds, fuel, and fertilizers, and plans his expenses for the season. However, by the time of harvest, the market situation may change—the price could both increase significantly and drop sharply.
If the price drops to 8,000 UAH per ton, the farm's profitability may be at risk. If, on the other hand, the price rises sharply, the buyer risks not receiving the required products or will be forced to buy them much more expensively.
To mitigate such risks, forward supply contracts are widely used in business practice. They allow the parties to agree in advance on the future delivery of products at a fixed price, ensuring predictability in business operations.
What is a forward contract
In legal terms, a forward is a derivative contract under which one party undertakes to transfer the underlying asset to the other party at a specified moment in the future, and the other party undertakes to buy the underlying asset at a price and on other terms determined by the parties at the time of concluding the contract (Part 4, Article 33 of the Law of Ukraine «On Capital Markets and Organized Commodity Markets»).
Forward contracts can be concluded regarding emission securities, other financial instruments, currency values, products, works, and services that have a monetary expression of value. All these things are the underlying assets of a derivative contract.
How does a forward differ from a regular delivery
A feature of a forward contract is its fixed-term nature and the fixation of a price for the future, which reduces market risks for both parties. This is precisely what distinguishes a forward contract from a standard supply agreement. The advantages of such a contract are obvious: for the supplier, it is the opportunity to receive in advance the funds needed to continue agricultural production, and for the buyer, it is to purchase products at economically favorable prices and protect themselves against failing to receive the required products, given the specific price fluctuations in the agricultural market and other factors.
Thus, regardless of the actual price of the underlying asset at the time of execution of the main contract, it will be sold or purchased at a pre-established fixed price.
On the one hand, due to price fluctuations, either party can, of course, end up either winning or losing; however, on the other hand, the seller, having lost a little on the price, gained the opportunity for guaranteed sales of their goods and avoided unnecessary expenses on finding buyers and advertising, and was able to more clearly plan and optimize the movement of goods and financial flows. Traditionally, physical forward contracts are used precisely in agriculture. This allows agricultural producers to guarantee the profitable sale of their future harvest regardless of the weather and price jumps.
Thus, concluding such an agreement provides the seller with additional financial opportunities, and the buyer with the opportunity to hedge against inflation risks and price changes.
Material terms of a forward contract
Essential terms that the parties must define in a forward contract for the purchase of agricultural products are:
– underlying asset (commodity);
- delivery time;
- quantity of goods;
- contract price;
– unit price.
Case law: fixed price and force majeure
However, when concluding forward contracts, it is necessary to consider not only the provisions of the legislation, but also the judicial practice regarding such contracts.
Thus, the courts have clearly established a practice regarding the definiteness of the price in a forward contract. In its ruling of June 20, 2018, in case No. 826/19192/16, the Supreme Court noted that the legal nature of a forward contract is solely that of a standardized document certifying a person's obligation to purchase (sell) securities, goods, or funds at a specified time and under specified conditions in the future, with the prices of such sale fixed at the time of concluding the contract.
Price fixing is an essential term of the contract; such a price must be specifically determined at the time of contract conclusion. Subsequent price changes, as well as the termination of a forward contract on the grounds of a price change, are prohibited.
In case No. 910/332/24, the parties concluded a contract in December 2022. Starting from August 14, 2023, due to military aggression, shelling, mobilization, and other circumstances recognized as force majeure, the performance of works was disrupted. The seller (plaintiff) notified the buyer (defendant) of the occurrence of force majeure circumstances, provided the relevant certificates from the Ukrainian CCI, but the defendant applied sanctions for late performance. Subsequently, the seller filed a statement of claim with the Commercial Court of the City of Kyiv, in which they asked the court to amend the terms of the contract and cancel the sanctions. However, the Commercial Court of the City of Kyiv dismissed the claim, believing that the force majeure circumstances were not proven, and since the contract was concluded during martial law, changes to its terms were unacceptable. The appellate court overturned the first-instance decision, satisfied the claim, and amended the contract, citing the existence of force majeure and its impact on the performance deadlines.
Instead, the Supreme Court in this case formulated a legal position emphasizing that the existence of force majeure circumstances precludes the possibility of amending the contract due to a substantial change in circumstances. In particular, the Supreme Court ruling states that the plaintiff could and should have foreseen, with a certain degree of diligence, the occurrence of difficulties in the performance of the contract related to the imposition of martial law, given that martial law had already been imposed throughout the territory of Ukraine at the time the contract was concluded. Therefore, the occurrence of the events cited by the plaintiff cannot be considered as grounds for amending certain clauses of the contract and the appendix thereto due to a substantial change in circumstances.
Crop failure and price changes: can the contract be terminated
The issue of fulfilling forward contracts became particularly relevant in 2020, when, due to a severe drought in certain regions of Ukraine, farmers faced a significant decrease in crop yields. According to official data, the total production of grain and leguminous crops in 2020 was about 65.4 million tons, which is almost 10 million tons less than the previous year.
Under such conditions, the fulfillment of previously concluded forward contracts became problematic for many producers, which led to a significant number of commercial disputes. It was during this period that the courts reviewed a number of cases regarding the performance of forward agricultural supply contracts, which essentially shaped the approach of judicial practice to the distribution of commercial risks between the parties to such contracts.
Generally, a change in the market price of goods, adverse weather conditions, and other similar factors are not recognized as a material change in circumstances that could serve as a ground for terminating a supply agreement, since these risks are ordinary commercial risks of the parties. Thus, in its decision of September 23, 2021, in case No. 902/252/21, the Commercial Court of Vinnytsia Region noted that weather conditions are of a general nature, constitute commercial risks of the parties to the supply agreement, and fully apply to both parties to the agreement rather than to the supplier alone; therefore, they cannot be classified as circumstances that the parties were guided by when concluding the disputed agreement, assuming they would not occur, and due to which the performance of the agreement would disrupt the balance of property interests of the parties and deprive the interested party of what it relied upon when concluding the agreement. Similar conclusions were reached by the Commercial Court of Rivne Region in its decision of March 1, 2021, in case No. 918/1163/20.
What to look out for when concluding
Therefore, when concluding a forward contract, it is advisable for the parties to pay attention to the following aspects:
- clear definition of the underlying asset (type, grade, product quality);
- determination of the place and conditions of delivery;
- payment procedure;
- liability of the parties for failure to perform the contract;
- procedure for confirming force majeure circumstances.
Detailing such terms minimizes the risks of disputes in the future.
Conclusions
Therefore, forward agricultural produce supply contracts are an important tool for managing commercial risks in the agrarian sector. They allow producers to secure the sale of their future harvest in advance, achieve financial predictability, and plan their production activities.
At the same time, the conclusion of such an agreement implies the acceptance by the parties of the risk of market changes. That is why special attention should be paid to the clear definition of the essential terms of the agreement, primarily the price, quantity, and delivery terms.
Case law demonstrates that courts consistently uphold the principle of the stability of forward contracts and do not allow them to be modified solely on the grounds of market price fluctuations or other ordinary commercial risks.
Thus, a properly executed forward contract can become an effective tool for planning business activity for both agricultural producers and buyers of agricultural products.