Work is done, but there is no money? How to recover a debt if the customer ignores the Acceptance Certificates

One of the most common problems in construction and any other business involving the performance of work is when you have done everything with high quality and on time, but the customer does not pay. They may ignore your calls, refuse to sign certificates of completion, or make petty and formal complaints about document processing, as well as cite temporary financial difficulties, and so on.

However, in most cases, the law will be on the side of the contractor. The customer's silence or unjustified refusal to sign the acceptance certificate legally means that the works have been accepted. However, the key to success in such disputes lies not only in the actual execution of the works, but also in the legally competent documentation of the process of their transfer and acceptance. A properly constructed strategy makes it possible to turn the customer's silence or unjustified refusal into the legal fact of acceptance of the works, which significantly strengthens the contractor's position in the event of debt collection through the courts.

Let's figure out how this works:

The contractor's strategy should aim to legally document the fact of «work acceptance,» even if the customer does not physically sign the documents. As soon as the acceptance of work is proven, the payment obligation becomes unconditional, and any subsequent refusals to sign or pay become unlawful.

The key document recording the completion of work and its transfer is the acceptance certificate (for example, standard forms No. KB-2v and No. KB-3 in construction). Article 882 of the Civil Code of Ukraine (CC of Ukraine) explicitly states that the transfer of work by the contractor and its acceptance by the customer is formalized by an act signed by both parties. This document performs several critically important functions:

  • confirms the execution of works in accordance with the terms of the agreement;
  • records the absence of comments from the customer;
  • in the vast majority of cases, it triggers the payment deadline.

Thus, the entire legal dispute regarding the payment for completed work often comes down to the status of this document. A customer who wishes to evade payment will try at any cost to avoid signing it. To prevent this from happening, one must be aware of and follow a certain algorithm of actions.

«Tacit consent» - an important principle of debt collection in such situations:

A key rule that every contractor/service provider must know, enshrined in the Civil Code of Ukraine and confirmed by numerous decisions of the Supreme Court: If you sent the acceptance certificates for completed work to the customer, and they did not sign them or provide a reasoned refusal within the period established by the contract, the work is considered accepted.

What is a «motivated refusal»? It is not just any remark, but only specific claims regarding the substance of the performed work.

Valid grounds for the customer not to sign the certificate may include:

  • Specific quality complaints: for example, «cracks on the wall» or «poorly laid tiles.».
  • Discrepancy in volumes: for example, «100 m² of fence was ordered, but 95 m² was built.».
  • Violation of terms or conditions of the agreement that directly affect the outcome.
  • Defects have been detected that make it impossible to use the result of the work.

Instead, unmotivated refusals, which do not constitute grounds for non-payment, are considered to be:

  • General phrases without specifics, for example, «the works were performed unsatisfactorily» or «the works do not comply with the contract.».
  • Formal errors in documents that do not affect the essence, such as a minor typo in the name of an object or an incorrect date, if it can be identified.
  • Reference to lack of funding.
  • Demand to provide documents not stipulated by the contract or law.

This list is not exhaustive and may vary in each individual situation.

Therefore, if the customer's remarks do not relate to quality, scope, or deadlines, but are merely formal or unspecific, the court will most likely recognize such a refusal as unjustified.

 How it works in practice: an example from a court case № 910/4394/24

Recently, a court examined precisely this kind of situation with the participation of our company's attorneys. The contractor completed capital repairs on a facility worth nearly 2 million UAH and sent the certificates to the customer for signature. The customer returned the documents twice for formal reasons: first, they demanded an additional certificate, and upon receiving it, they pointed out a purported error in the facility name in the certificates (the word «Adjustment» was added at the end). At the same time, they raised no objections regarding the quality or scope of the work itself.

The courts of first and appellate instances recognized such refusals as unfounded. Since the customer did not provide motivated comments on the merits of the work within the period stipulated by the contract, the work was deemed automatically accepted. In addition, the courts noted that the lack of budget allocations is not a ground for failing to pay for the completed work. As a result, the court ordered the customer to pay the entire amount of the debt. The customer did not appeal to the Supreme Court.

The position of the Supreme Court is well-established and states that the main thing is the fact of the work being performed, not the paperwork.

The Supreme Court consistently sides with bona fide contractors, emphasizing the principle of substance over form. This means that the actual performance of work is much more important than the ideal paperwork.

In its decisions, in particular in the ruling in the case of № 911/1981/20, the Supreme Court pointed out that improper documentation, in particular the failure of the customer to sign certificates without providing a motivated refusal to sign them within the terms specified by the contract and/or law, cannot in itself indicate non-performance of work, if its actual performance is confirmed by other evidence. It is the business transaction itself (the actual provision of services/performance of work) that creates legal consequences, rather than the primary documents. This legal position is well-established in judicial practice and protects contractors from unscrupulous customers who use formal deficiencies in documents as an excuse for non-payment for actually received results.

So, if the customer unreasonably refuses to sign the certificate, the certificate signed unilaterally by the contractor will be full-fledged evidence in court. And it will be the customer, not you, who will have to prove that their refusal was justified.

Step-by-step action plan for the contractor/contractor

To protect yourself against non-payment, follow a simple algorithm:

Check your contract. Even at the stage of drafting the agreement, make sure it includes a clause on the automatic acceptance of work («tacit consent») if the client does not provide a motivated refusal within a specified timeframe (for example, 5-10 business days).

Send the acts signed by your side correctly. Always send certificates officially by registered mail with a description of the enclosure. This is your ironclad proof that the customer received the documents and from what point the response time started.

Got a refusal? Analyze it. Read carefully what the client writes. If the rejection contains only formal remarks rather than specific complaints about quality or volume, feel free to consider it unjustified.

Write a motivated response to the refusal. Referring to the terms of the contract, the legal framework, and judicial practice, justify to the client why their refusal is unlawful and unacceptable. State the demand to pay for the performed works. In your response, it is advisable to inform the client that in the event of their refusal to pay, you will apply to the court.

File a lawsuit. If payment has not been received after this, go to court. You already have a strong position. The burden of proof that the works were not performed or were performed improperly now lies with the customer. Your task is to clearly present the chronology of events and evidence to the court.

CONCLUSION

The problem of non-payment for completed work, although widespread, should not be perceived as an inevitable business risk. It is a legal issue that has a clear and effective solution. It is important to have the right contract, document all steps, and not be afraid to stand up for your rights, relying on a clear position of the legislation and the courts. This turns completed work into guaranteed income rather than a cause for concern.

Although the presented algorithm is universal, every case has its own unique circumstances. Successful implementation of this strategy requires not only knowledge of the law, but also experience in resolving commercial disputes. Professional legal assistance at the stage of drafting a contract, conducting negotiations, or representation in court is an investment that guarantees the minimization of negative risks from unscrupulous counterparties.

If you encounter the issue of non-payment, we recommend first seeking legal advice to analyze your situation and develop an individual strategy to protect your interests.

CALL NOW
Top

Did you sign up for Business Lawyer?

A channel with legal advice and news for the successful development of your business

This website uses cookies to ensure you get the best experience on our website.

LEAVE THE PHONE NUMBER

Leave the phone number