Won the tender? What is next? The most common business mistakes during the performance of public procurement contracts

Public procurement has long been one of the largest markets for Ukrainian business. For many companies, fulfilling government contracts provides a significant portion of revenue, allows them to scale their operations, and enables them to work with stable customers. Participating in procurement through the Prozorro electronic system is nowadays often perceived as a completely straightforward process: prepare documents, offer a competitive price, win the tender, fulfill the contract, and receive payment.

That is precisely why most participants focus primarily on the procurement participation stage: gathering documents, confirming qualifications, analyzing tender documentation requirements, and calculating the bid price. Winning the tender is perceived as the main goal, and after signing the contract, many companies believe that the hardest part is already behind them.

However, practice shows the opposite. The greatest legal and financial risks arise precisely after the contract is signed. At this stage, businesses most frequently face penalties, customer claims, refusals to pay for completed works or services, contract termination, and litigation. The subject of such disputes is usually not the procurement process itself, but rather the improper fulfillment of contractual obligations.

In recent years, I have had to handle a significant number of disputes related to the performance of public procurement contracts. Regardless of the procurement sector—whether construction, design work, equipment supply, or the provision of services—the causes of conflicts turn out to be surprisingly similar. In most cases, they arise not from the contractor's bad faith, but from a misunderstanding of the specifics of executing procurement contracts. As a result, even a conscientious contractor or supplier may find themselves in a situation where they are forced to perform additional work at their own expense, pay penalties, or defend their rights in court.

The main reason for such situations is that businesses often view a procurement contract as a regular commercial contract. And this is the first and, perhaps, the most costly mistake.

In classical commercial relations, the parties can agree to postpone deadlines, change the cost of work or the volume of services, agree on additional work, or adjust certain terms of the contract. In public procurement, such freedom is substantially limited. A procurement contract is a continuation of the procurement procedure, is inextricably linked to the tender documentation and the winning bidder's tender offer, and the possibility of amending its terms is clearly defined by law. In addition, the execution of such contracts is under the constant control of state financial control authorities, which significantly influences the behavior of customers.

Given this, decisions that would be completely logical in ordinary business relations may turn out to be legally impossible in the field of public procurement. As a result, even a minor violation of deadlines or other contract terms often becomes the basis for the accrual of penalties, and sometimes for the refusal of payment or termination of the contract.

So how to avoid these traps? In this article, I propose to examine the most common mistakes made by businesses when executing procurement contracts, find out the causes of their occurrence, and determine the steps that will help minimize risks even before the dispute ends up in court.

Tender documentation: why most problems begin even before contract signing

The biggest mistake businesses make is that tender documentation is often perceived merely as a list of requirements to participate in a procurement. In reality, it is precisely at this stage that the future legal and financial risks of contract execution are laid down. A superficial review of the tender documentation is the first mistake that will subsequently have negative consequences for the bidder.

The vast majority of participants analyze tender documentation solely through the prism of winning the procedure: whether there is enough experience, employees, whether we meet the qualification criteria, and whether the package of documents is assembled correctly. Undoubtedly, these issues are important. However, they relate only to the stage of determining the winner.

It is important to consider that the tender documentation is not just an instruction for admission to bidding: this document is actually the basis of the future contract. According to the basic principles of procurement legislation, the terms of the procurement contract must not differ from the content of the winner's tender proposal. Therefore, various sections of the tender documentation may contain requirements that directly affect the cost of contract performance, the procedure for organizing work, and the possibility of meeting deadlines.

For example, it is in the tender documentation that the customer can provide for:

  • special procedure for approving certain stages of work or services;

  • the contractor's obligation to carry out author's or technical supervision without additional payment;

  • requirements regarding the permanent presence of the contractor's representative at the site;

  • special procedure for approval of materials or equipment;

  • shortened response times to customer comments;

  • the obligation to re-perform certain works or services at one's own expense;

  • additional warranty obligations;

  • increased requirements for the preparation of as-built documentation, etc.

If these nuances are not noticed at the proposal submission stage, additional requirements will have to be fulfilled at one's own expense, since failure to fulfill them entails the accrual of a penalty or the customer's refusal to sign the acceptance certificates. In fact, most risks are hidden not in the qualification requirements, but precisely in those terms that will determine the procedure for contract performance.

Also, as practice shows, most tender participants either do not know about or do not use their right to request clarification on procurement terms. The Law of Ukraine «On Public Procurement» grants participants the right to contact the procuring entity for clarifications regarding the provisions of the tender documentation even before the deadline for submitting bids expires. However, in practice, these tools are used much less often than they could be. The reasons vary: some do not want to waste time, some are afraid of «attracting unnecessary attention,» and others believe that the procuring entity will not change anything anyway.

Actually, if a certain provision of the documentation allows for different interpretations, one should not try to guess the customer's intent or interpret what is written at one's own discretion. After all, upon completion of the procurement procedure, it is these terms that will determine the content of the contractual relationship between the parties.

Also quite significant is the commission of formal and technical errors when submitting a tender bid. Although formal and technical errors in a tender bid may seem insignificant (for example, submitting a copy of a document instead of the original or a letter instead of a certificate of the established form), in practice they can have serious consequences.

To correct such discrepancies, the legislation provides a special mechanism. If, during the review of a tender offer, the customer discovers errors, they are obliged to publish a request for their elimination, and the participant has 24 hours to make the corrections. In the event of timely elimination of the discrepancies, the procurement procedure continues, and if the errors are not corrected, the tender offer is subject to rejection.

At the same time, this mechanism only works provided that the discrepancies were discovered by the customer itself. If the customer failed to notice the error and did not send a demand for its elimination, the contract may be concluded on the basis of a proposal that actually contains a violation. In such a case, during monitoring, the state financial control body may establish a violation of public procurement legislation. If the inspection takes place already after the conclusion of the contract, the conclusion based on the monitoring results may demand the termination of contractual relations.

Also, when analyzing the bidding documentation, it is important to assess the realism of the deadlines: whether there is enough time for equipment delivery, passing expert reviews, obtaining permits, or document approval by the customer. Sometimes it becomes obvious even at this stage that fulfilling the contract without violating the deadlines will be extremely difficult or even impossible. However, the desire to win the order often outweighs a realistic assessment of the risks.

In my opinion, even before submitting a tender offer, a company should conduct not only a legal analysis of the tender documentation, but also a kind of audit of the future contract. Its purpose is not a formal search for flaws, but to answer the main question — whether the company is capable of fulfilling the contract on the proposed terms and whether this contract will become financially unprofitable.

In other words, it is necessary to analyze not only the documents, but the procurement itself. It is precisely this approach that makes it possible to assess real risks even before participating in the bidding, avoid unjustified expectations, and make an informed decision.

Why a procurement contract does not work by the rules of ordinary business

Many companies submit a tender bid based on the assumption that if unforeseen circumstances arise during the performance of the contract, the parties will always be able to reach an agreement. That is exactly how the vast majority of commercial deals work. However, in the field of public procurement, this approach does not work.

At first glance, a public procurement contract differs very little from any other commercial contract. It likewise defines the subject matter, price, deadlines, rights and obligations of the parties, the procedure for accepting work or services, and liability for breach of obligations.

This very external similarity is often misleading. After signing the contract, many contractors continue to act as they are used to working with their commercial counterparties, expecting that, if necessary, it will be possible to negotiate an extension of the work deadlines, clarify the technical specifications, change the procedure for performing individual stages of work, agree on additional services, or revise the contract price.

In classic business legal relations, this is completely normal. The principle of freedom of contract allows parties to change its terms at any time by mutual agreement, provided this does not contradict the law. However, in the field of public procurement, this principle operates within very limited boundaries.

After concluding the contract, the parties are bound not only by its text, but also by the entire procurement procedure that preceded it. The procurement contract must be viewed as the final stage of the entire procedure.

The feature of such a contract is that it does not exist on its own. To interpret its content, not only the text of the agreement is used, but also the tender documentation and the winner's tender offer. All these documents form a single legal structure. Moreover, in public procurement, the contractor signs exclusively the version of the contract that was proposed by the customer in the tender documentation.

The Law of Ukraine «On Public Procurement» permits the modification of essential contract terms only in exceptional cases (in particular, in the presence of documented objective circumstances, changes in the price of goods, reduction of procurement volumes, or improvement of quality). In all other cases, even the mutual agreement of the parties is not a sufficient basis for making changes.

That is why the belief that any flaws in a tender offer can be corrected after the contract is concluded by signing an additional agreement is mistaken. In practice, such an approach can lead to negative legal consequences, in particular, to the establishment of a violation during procurement monitoring and the demand to terminate the contract.

Contract performance delay: what businesses most often expect and why it does not work

The largest number of disputes in this area arises from the violation of deadlines for the performance of obligations. At the same time, many contractors underestimate the consequences of even a minor delay, believing that a delay of one or several days will not be of significant importance or that the customer will «be understanding.» In practice, this is one of the most expensive mistakes: customers in the public sector almost always apply penalties for the slightest delay (even of a single day), since they themselves are under the threat of audits.

Another misconception is quite widespread as well—that if the performance of a contract has been complicated by martial law, air raid alerts, power outages, employee mobilization, or other circumstances, this is automatically sufficient for exemption from liability.

Actually, this is not the case. The mere fact of the existence of such circumstances does not exempt from liability. What is crucial is:

  • Did they really make the timely execution of the specific contract impossible?

  • Did the contractor inform the customer about this within the established deadline?

  • Can he prove with proper evidence the causal link between these circumstances and the delay?

Therefore, one should not expect that a reference to martial law or other well-known circumstances will automatically protect against the accrual of penalties. If there are risks of violating deadlines, the client must be notified in a timely manner, the circumstances hindering the performance of the contract must be documented, and, if possible, the situation should be resolved before the delay occurs.

The worst strategy for a contractor is silence. Hoping to complete the work with a slight delay and that the problem will resolve itself, the contractor wastes time. Instead, a timely official letter regarding circumstances affecting deadlines carries much greater legal weight than explanations provided after the delay has already occurred.

At the same time, the assessment of penalties by the customer does not mean they will have to be paid in full. If the violation was caused by objective circumstances and the amount of the fine is clearly disproportionate to the consequences, the law allows applying to the court with a request to reduce it.

When resolving such disputes, courts assess not only the fact of the delay, but also the conduct of the parties, the reasons for the breach, the degree of contract performance, and the proportionality of the sanctions. Therefore, if there is a risk of penalties being accrued, collect documents, record correspondence, and keep track of all actions aimed at performing the contract while the work is still underway. It is precisely this evidentiary base that will significantly influence the court's position.

Quality of work and document preparation: when formality costs money

Another common cause of disputes is the issue of the quality of performed works (services, goods) and the proper execution of relevant documents.

Unlike typical commercial relationships, where parties often rectify minor deficiencies even after signing certificates, public procurement customers are much more meticulous. And this is logical: any unjustified signing of certificates may become the subject of an audit by the State Audit Service, the Accounting Chamber, or law enforcement agencies.

That is why what would be considered an insignificant technical error in the commercial sector becomes grounds for refusing to accept work or returning documents in public procurement. This concerns not only the quality of work, but also the execution of acts, reports, as-built documentation, and so on.

It is especially worth considering that while the contractor is fixing remarks on document preparation, the contract performance deadlines continue to expire, which automatically creates the risk of late payment penalties being assessed.

Given this, recording results on paper is just as important as performing the work itself. In the field of public procurement, flawless documentation is often just as important as the quality of the delivered goods or provided services.

Conclusions and practical advice for business

To minimize financial and legal risks during the execution of procurement contracts, businesses should follow a few practical rules:

  • Analyze the tender documentation as a future contract, and not only as procurement participation conditions.

  • Do not ignore unclear or controversial provisions of the documentation. If certain terms allow for different interpretations or raise doubts, use the right to contact the customer for clarifications even at the procurement stage. This is much safer than trying to solve the problem after the contract has been concluded.

  • Realistically estimate the contract fulfillment deadlines. When planning participation in a procurement, consider potential delays in material supply, document approval, logistics, expert examinations, or other factors that may affect the fulfillment of obligations.

  • Do not delay written communication with the client. If circumstances arise that may affect the deadlines or the procedure for executing the contract, notify us immediately and exclusively in writing. Timely correspondence itself often becomes one of the key proofs of the contractor's good faith behavior.

  • Build the evidence base while the contract is still being performed. Keep documents confirming the reasons for delays or other circumstances beyond your control. In the event of a dispute, they can become decisive evidence.

  • Pay no less attention to document preparation than to the execution of the work itself. In public procurement, the proper drafting of certificates, reports, and other executive documentation is no less important than the quality of the delivered goods or performed works.

  • Do not consider the assessment of penalties as a final decision. If the violation occurred due to objective reasons and the amount of the penalty is disproportionate to the consequences of such violation, the law provides for mechanisms of judicial protection. At the same time, the effectiveness of such protection largely depends on how timely the contractor took care of proper documentary confirmation of their position.

The vast majority of disputes in the field of public procurement can be prevented. This does not always require complex court proceedings; often, it is enough to analyze the procurement terms in a timely manner, properly prepare documents, and ensure proper legal support at every stage of contract execution.

CALL NOW
Top

Did you sign up for Business Lawyer?

A channel with legal advice and news for the successful development of your business